CONSTRUCTION PROGRAM
PART 1 -GENERAL
1.01 DESCRIPTION
A. General
1. Promptly after reward of the contract, prepare and submit to
Engineer estimated construction progress program for the work, with sub-programs
of related activities which are essential to its progress.
2. Submit revised progress programs periodically.
B. Related Work Specified Elsewhere
1. General Conditions of Contract: Program to be finished.
2. Section 01110: Summary
of Work.
3. Section 01312: Project
Meeting
4. Section 01334: Shop
Drawings, and Product Data.
1.02 FORM OF SCHEDULES
A. Prepare programs in computerized format employing such
programs as CPM, GANNT and the like, as indicated by the Engineer.
B. Prepare Network Analysis system as requested by Engineer.
C. Identification of listings: By major specification section
numbers.
1.03 CONTENT OF PROGRAMMES
A. Construction Progress Programs:
1. Show the complete sequence of construction by activity.
2. Show the dates for the beginning, and completion of, each
major element of construction specifically list:
a. Site clearing.
b. Site Utilities.
c. Foundation work.
d. Structural framing.
e. Equipment installations.
f. Others as required by Engineer
3. Show projected percentage of completion
for each item, as of the first day of each month.
B. Submittal
Schedule for Shop Drawings, Product Data and Samples Show:
1. The
Dates for Contractor’s submittals will be required from the Engineer.
1.04 PROGRESS
REVISIONS
A. Indicate
progress of each activity to date of submission.
B. Show
changes occurring since previous submission of program:
1. Major
changes in scope.
2. Activities
modified since previous submission.
3. Revised
projections of progress and completion.
C. Provide
a narrative report as needed to define:
1. Problem
areas, anticipated delays, and the impact on the program.
2. Corrective
action recommended, and its effect.
3. The
effect of changes on programs of others main contractors.
1.05 SUBMISSIONS
A. Submit
initial programs within 21 days after signature of contract.
1. Engineer
will review programs and return review copy within 10 days after receipt.
2. If
required, resubmit within 7 days after return of review copy.
B. Submit
revised progress programs with each application for payment.
C. Submit
the number of reproducible which the Contractor requires, plus two copies will
be retained by the Engineer.
1.07 DISTRIBUTION
A. Distribution
copies of the reviewed programs to:
1. Job
site file
2. Sub-contractors
B. Instruct
recipients to report promptly to the Contractor, in writing, any problems
anticipated by the projections shown in the programs.
PART 2 -PRODUCTS
NOT USED
PART 3 -EXECUTION
NOT USED