Thursday, October 10, 2013

Civil Engineering Specifications -



COORDINATION

PART 1 - GENERAL

1.01     SUMMARY

A.         Section includes
Contractor’s Agent will coordinate the work of all sub-contractors.

B.         Related sections
1. Conditions of the contract: Contractor’s superintendence.
2. Section 01110:        Summary of work.
3. Section 01320:        Construction Programs.
4. Section 01334:        Shop drawings, product data and samples.
5. Section 01510:        Temporary utilities and facilities.
6. Section 01732:        Cutting and Patching.
7. Section 01780:        Project contract close-out procedures.

1.02     CONSTRUCTION ORGANIZATION AND START-UP
A.         Contractor’s Agent shall establish on-site lines of authority and communications:
1.   Schedule and conduct reconstruction meeting and progress meetings as specifies in section 01312.

2.   Establish procedures for inter-project communications:
a.   Submittals.
b.   Reports and records.
c.   Recommendations.
d.   Coordination drawings.
e.   Schedules.
f.    Resolution of conflicts.

3. Interpret contract documents:
a.   Consult with consultant to obtain interpretation.
b.   Assist in resolution of question or conflicts which may arise.
c.   Transmit written interpretations to subcontractors, and to other concerned parties.

4. Assist in obtaining permits and approvals:
a.   Building permits and special permits required for work or for temporary facilities.
b.   Verify that subcontractors have obtained inspections for work and for temporary facilities.

5. Control the use of site:
Where the work of one subcontractor will be installed in close proximity to work of other trades or where there is evidence that the work of the onr will interfere with work of others, he still assist in working out space conditions to make a satisfactory adjustment.

1.03     CONTRACTOR’S AGENT’S DUTIES

A.         Construction programs
1.         Prepare a detailed program of basic operations for all subcontractors:
a.   Each subcontractor shall prepare sub-programs to comply with critical phases.
2.         Monitor programs as work progresses:
a.   Identify potential variances between programs and probable completion dates for each phase.
b.   Recommend to Owner adjustments in programs to meet required completion dates.
c.   Adjust programs of sub contractors as required.
d.   Document changes in program submit to Owner Engineer and to involved sub-contractor.
3.         Observe work of each sub-contractor to monitor compliance with program:
a.   Verify that labor and equipment are adequate for the work and the program.
b.   Verify that product procurement programs are adequate.
c.   Verify that product deliveries are adequate to maintain program.
d.   Report non-compliance to Owner, with recommendation for changes.

B.         Process shop drawings, product data and samples:
1.         Prior to submittal to Engineer review for compliance with contract documents:
a.   Site dimensions and clearance dimensions.
b.   Relation to available space.
c.   Relation to other contracts and to other trades.
d.   Effect of any changes on the work of any other contracts or other trades.

C.        Prepare coordination drawings as required or if directed by the Engineer to resolve conflicts and to assure coordination of the work of or affected by mechanical and electrical trades, or by special equipment requirements. Scale not less than 1:50.
1.         Submit to Engineer.
2.         Reproduce and distribute copies to concerned parties after Engineer review.

D.        Inspection and testing:
1.         Inspect work to assure performance in accordance with requirements of contract documents.
2.         Administer special testing and inspections of suspect work.
3.         Reject work which does not comply with requirements of contract documents.
4.         Coordinate testing laboratory services:

a.   Verify that required laboratory personnel are present.
b.   Verify that tests are made in accordance with specified standards.
c.   Review test reports for compliance with specified criteria.
d.   Recommend and administer any required retesting.

E.         Monitor the use temporary utilities:
1.         Verify that adequate services are provided and maintained.

F.         Monitor subcontractor’s periodic cleaning:
1.         Enforce compliance with specifications.
2.         Resolve any conflicts.

G.        Change and substitutions:
1.         Recommend necessary or desirable changes to Owner and Engineer.
2.         Review subcontractor’s requests for changes and substitutions; submit recommendations to Owner and to engineer.
3.         Assist Engineer in negotiating variation orders.
4.         Promptly notify all subcontractors of pending changes or substitutions.

H.        Maintain Reports and records at job site available to Engineer and Owner.
1.         Daily log of progress of work of each subcontractor.
2.         Records:
a.   Subcontracts.
b.   Purchase orders
c.   Materials and equipment records.
d.   Applicable handbook codes and standards.
3.         Obtain information from subcontractors, and maintain file of record documents.
4.         Assemble documentation for handling of claims and disputes.

1.04     CONTRACTOR’S AGENT’S CLOSE-OUT DUTIES
A.         Mechanical and electrical equipment start-up:
1.         Coordinate check-out of utilities, operational systems and equipment.
2.         Assist in initial start-up and testing.
3.         Record dates of start of operation of systems and equipment.
4.         Submit to Owner written notice of beginning of guarantee period for equipment put into service.
B.         At completion of work of each subcontract, conduct an inspection to a assure that:
1.         Specified cleaning has been accomplished.
2.         Supervise correction and completion of work as established in certificate of substantial completion.






D.        Final completion:

1.         When each subcontractor determines that work is finally complete conduct an inspection to verify completion of work.
2.         Assist Engineer in inspection.

E.         Administration of contract close-out:
1.         Receive and review subcontractor’s final submittals.
2.         Transmit to Engineer with recommendations for action.

F.         Notes on drawings:
The technical / general Notes indicated on Engineering drawings are to be read in continuation with the contractual terms of this contract.

PART 2 - PRODUCTS
NOT USED

PART 3 - EXECUTION
NOT USED

AddThis

Search This Blog