SHOP
DRAWINGS, PRODUCT DATA
PART 1 - GENERAL
1.01 DESCRIPTION
A. General
Submit shop
drawings and product data required by contract documents.
B. Related Work Specified
Elsewhere
1. Conditions of the Contract: Quality of
materials and workmanship and tests.
2. Section 01320: Construction Programs.
Designate
in the construction program, or in a separate coordinated schedule, the dates
for submission and the dates that reviewed shop drawings, product data and samples
will be needed.
1.02 SHOP DRAWINGS
A.
Layouts,
schematics, descriptive literature, illustrations, schedules, performance and
test data, and similar materials furnished by the Contractor to explain in detail
specific portions of the work.
B. Within 30 calendar days of
receipt of Notice to proceed, submit to the Owner a program of shop drawings
submissions.
C. Drawings shall be presented
in a clear and through manner.
D. Details shall be identified
by reference to sheet and details, schedule or room numbers shown on contract drawings.
E. Minimum sheet size: A3
1.03 PRODUCT DATA
A. Preparation
1. Clearly mark each copy to identify
pertinent products or models.
2. Show performance characteristics and
capacities.
3. Show dimensions and clearances
required.
4. Show wiring or piping diagrams and
controls.
B.
1. Modify drawings and diagrams to delete
information which is not applicable to the work.
2. Supplement standard information to
provide information specifically applicable to the work.
1.04 CONTRACTOR RESPONSIBILITIES
A. Review shop drawings,
product data and samples prior to submission.
B. Determine and verify:
1. Site measurements.
2. Site construction criteria.
3. Catalogue numbers and similar data.
4. Conformance with specifications.
C. Coordinate each submittal with
requirements of the work and of the Contract Documents.
D. Begin no fabrication or work
which requires submittals until return of submittals with Engineer approval.
E. If material or equipment is
installed before it is approved, the Contractor shall be liable for its removal
and replacement at no extra charge to the Owner; if, in the opinion of the
Engineer the material or equipment does not meet the intent of the drawings and
specifications.
1.05 SUBMISSION REQUIREMENTS
A. Make submittals promptly in
accordance with approved schedule, and in such sequence as to cause no delay in
the work or in the work of any other Contractor.
1.06 DISTRIBUTION
A. Distribute reproductions of
Shop Drawings and copies of product data which carry the Engineer stamp of
approval to:
1. Job site file.
2. Record documents file.
3. Subcontractors.
4. Supplier or fabricator.
B. Distribute samples, which
carry the Engineer, stamp or approval as directed by the Consultant.
1.07 ENGINEER
A. Review submittals with
reasonable promptness and in accord with schedule.
B. Affix stamp and initials or
signature, and indicate requirements for re-submittal, or approval of
submittal.
C. Return submittals to
Contractor for distribution, or for re-submission.
1.08
A. Acceptance of key personnel
and Engineers deployed by the Contractor for the design and production of shop
drawings is subject to the approval of the Engineer.
B. In case an independent
design office is used by the Contractor for preparation of design details,
calculations, placement drawings etc. Contractor shall submit detailed documentation
as required by the Engineer, concerning the design agency to the Engineer for approval
furnishing the complete details of key personnel, Engineers etc. Contractor
shall only use the agency as approved by the Engineer.
C.
performance,
or a representative of the design office shall always be available at site
office of the Contractor with an update status of drawings to update the
Engineer on the status and submission schedule of submittals.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED